Measurement & maintenanceProzanta Method Standard · v1.0 · juli 2026

OEE measurement

OEE Measurement

An OEE measurement makes equipment losses visible and prioritisable: Availability × Performance × Quality, tallied honestly and consistently, coupled to daily reaction. The goal is not the number — it is the conversation and the actions the number forces.

1 week of setup + 2-4 weeks of baseline before the first conclusionsProduction engineering + operators + team leader

Use the method when

  • Capacity feels tight, but no one can say precisely where the time is lost
  • An investment discussion: before buying capacity, you must know the utilisation of the existing
  • As a shared language for loss across shifts and departments

Don’t use it when

  • On non-bottlenecks “because we measure everything” — measure where the number is to drive decisions
  • As a performance metric for individuals or to compare fundamentally different plants — OEE is compared with itself over time

Before you start

1

The definition is agreed IN WRITING before the first measurement: what counts as planned time, and what doesn’t

2

The ideal cycle time per product is fixed (design/nameplate speed — not “what we usually run”)

3

The recording is realistic for the operators: better simple and complete than detailed and full of holes

The standard

How to do it — step by step

01

Set the honest definition

½ dag

Decide once: planned production time = total time minus DECIDED exclusions (no orders, planned maintenance if kept outside). Changeovers, cleaning during operation, breaks with the line running, waiting for material — all of that is LOSS, not exclusion. Write the definition down; it must never be negotiated when the number disappoints.

02

Set up recording of the six big losses

2-3 dage

Stops are recorded with a cause (breakdown, changeover, material, etc.) — including the short ones. Minor stops under, say, 5 minutes may be recorded with a tally button rather than text; what matters is that they are counted, for they typically sum to more than the big breakdowns. Quality loss: scrapped + reworked parts, incl. start-up scrap.

03

Calculate the three factors — separately

automatisk/dagligt

Availability = running time ÷ planned time. Performance = (ideal cycle time × parts produced) ÷ running time. Quality = good parts ÷ parts produced. OEE = the product. Always report the three factors together with the total — it is the factors that show where the effort should go.

04

Establish a baseline without reacting

2-4 uger

2-4 weeks of measurement before concluding: the natural variation must be known before a change can be called a change. Use the period to validate the recording — compare recorded time with total time; holes in the accounting are recording errors.

05

Couple to the board meeting and Pareto

løbende

Yesterday’s OEE and biggest loss cause on the board every morning. Weekly/monthly: a Pareto over loss causes — the two or three biggest get an A3 or SMED effort. Without this coupling, OEE is an accounting record; with it, it is a management tool.

06

Benchmark honestly

kvartalsvist

Compare primarily with your own baseline. The established references (world class ≈ 85%, typical unoptimised ≈ 60%, Nakajima 1988) are used as a bearing — and contribute anonymously to the Danish OEE Index for a Danish reference.

The classic mistakes

How it goes wrong in practice — and this is where most implementations part ways.

The definition is dressed up when the number disappoints

The temptation to move changeovers out of planned time is constant. Each move makes the number prettier and more useless — the capacity is the same, only the visibility is gone.

OEE as a whip

If the number is used to judge operators, the recording’s honesty dies in a week — and with it the whole measurement. OEE measures the system, not people.

Measurement without reaction

An OEE number no one acts on is wasted recording work — and the operators know it before management. The reaction cadence (board + Pareto + efforts) IS the purpose of the measurement.

Related standards

The standard is free. The anchoring is the craft.

The method only works when it becomes daily routines and leadership behaviour. The operations check shows in 4 minutes where your operations stand — and what should come first.