Metrics & analysisOverall Equipment Effectiveness

What is OEE?

OEE (Overall Equipment Effectiveness) measures how large a share of the planned production time actually produces good parts. OEE = Availability × Performance × Quality. World class is reckoned at ≈ 85%; typical unoptimised plants sit around 60% (Nakajima, 1988).

The three factors each isolate a type of loss: Availability captures stops (breakdowns, changeovers), Performance captures speed loss (reduced pace, minor stops), Quality captures defective parts and start-up scrap. An OEE of 60% means 40% of the planned time is lost — typically without anyone being able to see where.

OEE’s value is not the number but the conversation: a shared, honest definition of loss makes capacity waste visible and prioritisable. The classic mistake is to “dress up” OEE by moving losses outside planned time.

From metric to your own numbers

A key figure only means something when it sits on your own operation. Calculate your OEE in two minutes and see where capacity is lost, and how much there is to gain.